Deemed-to-Satisfy Provision · NCC 2025 Volume One

F1D4 Provision of drainage and grading to external areas

Part F1 Water management

Open F1D4 on NCC Online ↗

A concrete roof, balcony, podium or similar part of a building must have—

a drainage system complying with F1D3 that incorporates sufficient overflow provision: and

its structural substrate graded with a minimum fall of 1:80 in the plane of the substrate to suit the drainage system required by (a); and

a minimum 70 mm step down from the surface level of the internal floor structural substrate to the adjacent surface level of the external structural substrate, where applicable; and

a monolithic hob that is integral with the structural substrate, at least 70 mm high, installed at the outer perimeter, except where the perimeter of the roof, balcony, podium or similar part of the building drains directly to a gutter.

Notes

The invert level of overflow provision referred to in F1D4(a) must be installed not less than 20 mm below any adjacent internal floor structural substrate.

For the purposes of Section F, the plane of the floor or substrate is taken to mean the predominant fall of the surface in question, typically perpendicular to bounding walls and is not a reference to the diagonal intersection between planes.

For the purposes of this Part, a tile bed, screed, topping or similar component is not considered a structural substrate except within planter boxes where it can be used to achieve the minimum fall of 1:80.

F1D4(d) does not prevent penetration of a hob for the provision of overflow.

The minimum 70 mm step down reference in F1D4(c) is not intended to refer to the minimum waterproofing termination height specified in AS 4654.2. Where AS 4654.2 requires a termination height greater than 70 mm, the waterproof membrane termination can be extended by suitable means above the 70 mm concrete set down.

Changed since NCC 2022. See NCC 2022 Volume One F1D4, or show what changed.

Exposed joints in the drainage surface on a A concrete roof, balcony, podium or similar horizontal surface part of a building must have — be protected a drainage system complying with F1D3 that incorporates sufficient overflow provision: and its structural substrate graded with a minimum fall of 1:80 in accordance the plane of the substrate to suit the drainage system required by (a); and a minimum 70 mm step down from the surface level of the internal floor structural substrate to the adjacent surface level of the external structural substrate, where applicable; and a monolithic hob that is integral with Section 2.9 the structural substrate, at least 70 mm high, installed at the outer perimeter, except where the perimeter of AS 4654.2; and not be located beneath or run through a planter box, water feature the roof, balcony, podium or similar part of the building. building drains directly to a gutter. Notes The invert level of overflow provision referred to in F1D4(a) must be installed not less than 20 mm below any adjacent internal floor structural substrate. For the purposes of F1D4, an exposed joint Section F, the plane of the floor or substrate is taken to mean the predominant fall of the surface in question, typically perpendicular to bounding walls and is not a construction joint, control joint, expansion joint, contraction joint reference to the diagonal intersection between planes. For the purposes of this Part, a tile bed, screed, topping or movement joint and includes an exposed joint which similar component is directly below not considered a drainage surface. structural substrate except within planter boxes where it can be used to achieve the minimum fall of 1:80. F1D4(d) does not prevent penetration of a hob for the provision of overflow. The minimum 70 mm step down reference in F1D4(c) is not intended to refer to the minimum waterproofing termination height specified in AS 4654.2. Where AS 4654.2 requires a termination height greater than 70 mm, the waterproof membrane termination can be extended by suitable means above the 70 mm concrete set down.

Removed words are struck through; added words are highlighted. Comparison of the text only.

Can't meet F1D4? A Performance Solution must meet the Performance Requirements it satisfies: F1P1. Start a Performance Solution →

Clauses referred to

Defined terms used