NCC 2025 Volume One
Part F1 Water management
23 clauses · Open on NCC Online ↗
- F1O1 ObjectiveThe Objective of this Part is to— safeguard occupants from illness or injury and protect the building from damage caused by the entry of water; and…
- F1F1 Protection from waterA building, including any associated sitework, is to be constructed in a way that protects— people from the adverse effects of water; and other…
- F1F2 Resistance to rising damp and ground waterA building is to be resistant to the effects of water from the ground.
- F1P1 Managing rainwater impact on the building and adjoining propertiesWater, including water on the surface of the allotment that is collected by a building or associated sitework, must be redirected to a drainage…
- Table F1V1a Risk factors and scoresRisk factor | Category | Risk severity | Score Wind region | Region A0-5 (AS/NZS 1170.2) | Low to medium | 0 Region B1-2 (AS/NZS 1170.2) Region C…
- Table F1V1b Cyclic pressureStage number | Serviceability wind pressure (%) Min | Max 1 | 15 | 30 2 | 20 | 40 3 | 30 | 60
- F1V1 WeatherproofingCompliance with F1P1 for weatherproofing of an external wall is verified when— a prototype passes the procedure described in (2); and the external…
- F1D1 Deemed-to-Satisfy Provisions SAWhere a Deemed-to-Satisfy Solution is proposed, Performance Requirements F1P1 is satisfied by complying with F1D2 to F1D15. (2) Where a Performance…
- F1D2 Application of Part SAF1D4 to F1D7 and F1D10 do not apply to a roof with a covering complying with F1D12(a) to (d). (2) F1D3 to F1D7 and F1D10 do not apply to— timber…
- F1D3 Stormwater drainageStormwater drainage must be designed and constructed in accordance with AS/NZS 3500.3.
- F1D4 Provision of drainage and grading to external areasA concrete roof, balcony, podium or similar part of a building must have— a drainage system complying with F1D3 that incorporates sufficient…
- F1D5 Substrate materialsIn a building or part of a building, where a roof, balcony, podium, or similar part of a building is constructed of concrete, it must comply with AS…
- F1D6 Exposed jointsExposed joints in the drainage surface on a roof, balcony, podium or similar horizontal surface part of a building must— be located on the ridge…
- F1D7 External waterproofing membranesA roof, balcony, podium or similar horizontal surface part of a building must be provided with a waterproofing membrane — consisting of materials…
- F1D8 Damp-proofing SAExcept for a building covered by (3), moisture from the ground must be prevented from reaching— the lowest floor timbers and the walls above the…
- F1D9 Damp-proofing of floors on the ground SAIf a floor of a room is laid on the ground or on fill, moisture from the ground must be prevented from reaching the upper surface of the floor and…
- F1D10 Surface finishesIn a building or part of a building, the flooring or surface finish of a roof, balcony, terrace, podium, or similar part of a building must be—…
- Table F1D11 Subfloor openings and ground clearanceClimatic zone (see Figure F1D11) | Minimum aggregate subfloor ventilation openings without a membrane (mm2/m of wall) | Minimum aggregate subfloor…
- F1D11 Subfloor ventilationSubfloor spaces must— be provided with openings in external walls and internal subfloor walls in accordance with Table F1D11 for the climatic zones…
- F1D12 Roof coveringsA roof must be covered with— roof tiles complying with AS 2049, fixed in accordance with AS 2050; or metal sheet roofing complying with AS 1562.1;…
- F1D13 SarkingSarking-type material used for weatherproofing of roofs and walls must comply with AS 4200.1 and AS 4200.2.
- F1D14 Glazed assembliesSubject to (2) and (3), the following glazed assemblies in an external wall, must comply with AS 2047 requirements for resistance to water…
- F1D15 Wall claddingExternal wall cladding must comply with one or a combination of the following: Masonry, including masonry veneer, unreinforced and reinforced…