Specification clause · NCC 2025 Volume One
S13C5 Wires and cables
Specification 13 Penetration of walls, floors and ceilings by services · NCC 2019: Spec C3.15: 5
If a wire or cable or cluster of wires or cables penetrates a floor, wall or ceiling—
the opening must be neatly formed, cut or drilled and no closer than 50 mm to any other service; and
the opening must be no larger in cross-sectional area than—
2000 mm2 if only a single cable is accommodated and the gap between cable and wall, floor or ceiling is no wider than 15 mm; or
500 mm2 in any other case; and
the gap between the service and the wall, floor or ceiling must be fire-stopped in accordance with S13C7.
Same wording in NCC 2022 Volume One. See NCC 2022 Volume One S13C5.