7.5.1 Application

Part 7.5 Timber and composite wall cladding · NCC 2019: 3.5.4.1

Open 7.5.1 on NCC Online ↗

(1) Compliance with Part 7.5 for wall cladding is achieved if—

it is installed in accordance with—

7.5.2 for timber cladding, including weatherboards and profiled boards; and

7.5.3 for fibre-cement and hardboard wall cladding boards; and

7.5.4 for fibre-cement, hardboard and plywood sheet wall cladding; and

fibre-cement sheet eaves where provided, are installed in accordance with 7.5.5; and

openings and penetrations in cladding are flashed in accordance with 7.5.6; and

the bottom surface of the cladding terminates in accordance with 7.5.7; and

parapets, where provided, are capped in accordance with 7.5.8.

(2) Part 7.5 need not be complied with if H1D7(5) is complied with.

Same wording in ABCB Housing Provisions 2025. See ABCB Housing Provisions 2025 7.5.1.

Clauses referred to