Deemed-to-Satisfy Provision · NCC 2022 Volume One

D3D3 Fire-isolated stairways and ramps

Part D3 Construction of exits · NCC 2019: D2.2

Open D3D3 on NCC Online ↗

A stairway or ramp (including any landings) that is required to be within a fire-resisting shaft must be constructed—

of non-combustible materials; and

so that if there is local failure it will not cause structural damage to, or impair the fire-resistance of, the shaft.

Same wording in NCC 2025 Volume One. See NCC 2025 Volume One D3D3.
Can't meet D3D3? A Performance Solution must meet the Performance Requirements it satisfies: D1P1, D1P2, D1P3, D1P4, D1P5, D1P6, D1P8, D1P9. Start a Performance Solution →