A Class 9b assembly building which is an exhibition hall must be provided with—

automatic shutdown of any air-handling system (other than miscellaneous exhaust air systems installed in accordance with Sections 5 and 6 of AS 1668.1) which does not form part of the smoke hazard management system, on the activation of—

smoke detectors installed complying with Specification 20; and

any other installed fire detection and alarm system, including a sprinkler system complying with Specification 17; and

where the floor area is more than 2000 m2 and not more than 3500 m2—

an automatic smoke exhaust system complying with Specification 21; or

if the building is single storey, automatic smoke-and-heat vents complying with Specification 22; or

a sprinkler system (other than a FPAA101D or FPAA101H system) complying with Specification 17; and

where the floor area is more than 3500 m2, a sprinkler system (other than a FPAA101D or FPAA101H system) complying with Specification 17 and—

an automatic smoke exhaust system complying with Specification 21; or

automaticsmoke-and-heat vents complying with Specification 22, if the building is single storey.

Same wording in NCC 2025 Volume One. See NCC 2025 Volume One E2D17.
Can't meet E2D17? A Performance Solution must meet the Performance Requirements it satisfies: E2P1, E2P2. Start a Performance Solution →

State and territory variations all clauses side by side →

Defined terms used