(1) This clause applies to a Class 9b assembly building where the building or part of the building is used as a theatre or public hall which—

is a school assembly, church or community hall, and has a stage and any backstage area with a total floor area of more than 300 m2; or

is not a school assembly, church or community hall, and has a stage and any backstage area with a total floor area of more than 200 m2; or

has a stage with an associated rigging loft.

(2) A building or part of a building referred to in (1) must be provided with—

an automatic smoke exhaust system complying with Specification 21; or

if the building is single storey, automatic smoke-and-heat vents complying with Specification 22.

Same wording in NCC 2025 Volume One. See NCC 2025 Volume One E2D18.
Can't meet E2D18? A Performance Solution must meet the Performance Requirements it satisfies: E2P1, E2P2. Start a Performance Solution →

State and territory variations all clauses side by side →

Defined terms used