Deemed-to-Satisfy Provision · NCC 2022 Volume One

E2D9 Buildings not more than 25 m in effective height: Class 5, 6, 7b, 8 and 9b buildings

Part E2 Smoke hazard management · NCC 2019: Table E2.2a

Open E2D9 on NCC Online ↗

(1) A building not more than 25 m in effective height that—

is a Class 5 or 9b school building or part of a building having a rise in storeys of more than 3; or

is a Class 6, 7b, 8 or 9b building (other than a school) or part of a building having a rise in storeys of more than 2; or

has a rise in storeys of more than 2 and contains—

a Class 5 or 9b school part; and

a Class 6, 7b, 8 or 9b (other than a school) part,

must meet the requirements of (2).

(2) A building referred to in (1) must be provided with—

in each required fire-isolated stairway, including any associated fire-isolated passageway or fire-isolated ramp, an automatic air pressurisation system for fire-isolated exits in accordance with AS 1668.1; or

a zone pressurisation system between vertically separated fire compartments in accordance with AS 1668.1, if the building has more than one fire compartment; or

an automatic smoke detection and alarm system complying with Specification 20; or

a sprinkler system (other than a FPAA101D or FPAA101H system) complying with Specification 17.

(3) For the purposes of (2), vertically separated fire compartments are fire compartments above and below each other, and not fire compartments within the same storey.

Same wording in NCC 2025 Volume One. See NCC 2025 Volume One E2D9.
Can't meet E2D9? A Performance Solution must meet the Performance Requirements it satisfies: E2P1, E2P2. Start a Performance Solution →

Defined terms used