Deemed-to-Satisfy Provision · NCC 2022 Volume Three

B5D1 Deemed-to-Satisfy Provisions

Part B5 Cross-connection control · NCC 2019: B5.1

Open B5D1 on NCC Online ↗

(1) Where a Deemed-to-Satisfy Solution is proposed, Performance Requirement B5P1 is satisfied by complying with B5D2 to B5D6.

(2) Where a Performance Solution is proposed, the relevant Performance Requirements must be determined in accordance with A2G2(3) and A2G4(3) as applicable.

Changed in NCC 2025 (minor wording). See NCC 2025 Volume Three B5D1, or show what changed.

(1) Where a Deemed-to-Satisfy Solution is proposed, Performance Requirement B5P1 is satisfied by complying with B5D2 to B5D6. B5D7. (2) Where a Performance Solution is proposed, the relevant Performance Requirements must be determined in accordance with A2G2(3) and A2G4(3) as applicable.

Removed words are struck through; added words are highlighted. Comparison of the text only.