C2P4 Ventilation
Part C2 Sanitary drainage systems · NCC 2019: CP2.1
(1) A sanitary drainage system must ensure there is adequate ventilation to avoid foul air and gases accumulating in the sanitary drainage and sewerage system.
(2) A sanitary drainage system must ensure that ventilation is provided to avoid hydraulic load imbalance such that—
there is less than a 1% likelihood during the annual peak hour that when any fixture discharges, air pressure at any trap seal exceeds ±375 Pa difference from atmospheric pressure; or
an equivalent level of safety to human health is achieved as a system complying to (a).
Changed in NCC 2025 (minor wording). See NCC 2025 Volume Three C2P4, or show what changed.
(1) A sanitary drainage system must ensure there is adequate … — there is less than a 1% likelihood during the annual peak hour that when any fixture discharges, air pressure at … human health is achieved as a system complying to (a).