Delete clause C3P5 and insert TAS C3P5 as follows:

On-site wastewater management systems that facilitate on-site storage, treatment, disposal or re-use of wastewater must be designed and constructed—

with required treatment and storage capacity for the volume and make up of waste and frequency of discharge for disposal; and

with required size, strength and rigidity for the nature, flow rates, volume of wastes and/or waste products which must be processed; and

using materials which are impervious both to the waste for which disposal is required and to water; and

to avoid the likelihood of surface water and stormwater entering the system; and

so that access or inspection openings provided for desludging and maintenance terminate at or above finished surface level.

so that the installation throughout its serviceable life will continue to satisfy the requirements of C3P1 to C3P9.