Performance Requirement · NCC 2022 Volume Three

C3P5 General requirements

Part C3 On-site wastewater management

Open C3P5 on NCC Online ↗
Varied in TAS, VIC. Check the variation for your state.

On-site wastewater management systems that facilitate on-site storage, treatment, disposal or re-use of wastewater must be designed and constructed—

with required treatment and storage capacity for the volume and make up of waste and frequency of discharge for disposal; and

with required size, strength and rigidity for the nature, flow rates, volume of wastes and/or waste products which must be processed; and

using materials which are impervious both to the waste for which disposal is required and to water; and

to avoid the likelihood of surface water and stormwater entering the system.

Same wording in NCC 2025 Volume Three. See NCC 2025 Volume Three C3P5.

State and territory variations all clauses side by side →

Defined terms used