Victoria variation · NCC 2022 Volume Three

VIC C3P5 General requirements

Part C3 On-site wastewater management · varies C3P5 General requirements

Open on NCC Online ↗

Delete clause C3P5 and insert VIC C3P5 as follows:

On-site wastewater management systems that facilitate on-site storage, treatment, disposal or re-use of wastewater must be designed, constructed, installed, replaced, repaired, altered and maintained—

with required treatment and storage capacity for the volume and make up of waste and frequency of discharge for disposal; and

with required size, strength and rigidity for the nature, flow rates, volume of wastes and/or waste products which must be processed; and

using materials which are impervious both to the waste for which disposal is required and to water; and

to avoid the likelihood of surface water and stormwater entering the system; and

in accordance with the requirements and agreement of the relevant authority having jurisdiction.

Not in NCC 2025. No VIC C3P5 in NCC 2025 Volume Three.

The national clause

Other states and territories