7.5.4 Sheet wall cladding

Part 7.5 Timber and composite wall cladding · NCC 2019: 3.5.4.4

Open 7.5.4 on NCC Online ↗

(1) Fibre-cement sheet wall cladding must—

comply with AS/NZS 2908.2 or ISO 8336; and

be fixed in accordance with Table 7.5.4a.

(2) Hardboard sheet wall cladding must—

comply with AS/NZS 1859.4 for exterior grade; and

be fixed in accordance with Table 7.5.4b.

(3) Structural plywood wall cladding must—

comply with AS/NZS 2269.0; and

be fixed in accordance with Table 7.5.4c.

Table 7.5.4a Stud and fixing spacings for 6 mm fibre-cement sheet wall cladding

Wind class

Maximum stud spacing (mm)

Maximum nail spacing within 1.2 m of the external corners of the building (mm) Note 1

Maximum nail spacing elsewhere (mm) Note 1

N1

≤ 1.2 m of external building corners: 600 Elsewhere: 600

Body: 300, Edges: 200

Body: 300, Edges: 200

N2

≤ 1.2 m of external building corners: 600 Elsewhere: 600

Body: 200, Edges: 200

Body: 300, Edges: 200

N3

≤ 1.2 m of external building corners: 450 Elsewhere: 600

Body: 200, Edges: 200

Body: 200, Edges: 200

Table Notes

Maximum nail spacing using 2.8 mm fibre-cement nails.

Fixings must be located not less than 50 mm from the edge of all corners.

Fasteners must penetrate not less than 30 mm into a timber frame.

Wall cladding may be fixed through timber or metal battens attached to the wall frame in accordance with AS 1684.2, AS 1684.3, AS 1684.4 or NASH standard as appropriate (see fixing requirements for roof battens) so long as the minimum penetration into the wall frame is achieved.

Table 7.5.4b Stud and fixing spacings for 9.5 mm thick hardboard sheet wall cladding

Wind class

Maximum stud spacing (mm)

Maximum nail spacing within 1.2 m of the external corners of the building (mm) Note 1

Maximum nail spacing elsewhere (mm) Note 1

N1

600

Body: 300, Edges: 150

Body: 300, Edges: 150

N2

600

Body: 300, Edges: 150

Body: 300, Edges: 150

N3

600

Body: 300, Edges: 150

Body: 300, Edges: 150

Table Notes

Maximum nail spacing using 2.8 mm galvanised clouts or flat head nails.

Fixings must be positioned a minimum of 12 mm from the edge of the sheet and not less than 50 mm from the edge of all corners.

Fasteners must penetrate not less than 30 mm into the timber frame.

Wall cladding may be fixed through timber or metal battens attached to the wall frame in accordance with AS 1684.2, AS 1684.3, AS 1684.4 or NASH standard as appropriate (see fixing requirements for roof battens) so long as the minimum penetration into the wall frame is achieved.

Table 7.5.4c Stud and fixing spacings for plywood wall cladding equal to or greater than 6.5 mm thick

Wind class

Maximum stud spacing (mm)

Maximum nail spacing within 1.2 m of the external corners of the building (mm) Note 1

Maximum nail spacing elsewhere (mm) Note 1

N1

600

Body: 200, Edges: 100

Body: 200, Edges: 150

N2

600

Body: 200, Edges: 100

Body: 200, Edges: 150

N3

600

Body: 150, Edges: 100

Body: 200, Edges: 150

Table Notes

Maximum nail spacing using 2.8 mm or 3.5 mm galvanised clouts or flat head nails.

Fixings must be positioned a minimum of 12 mm from the edge of the sheet and not less than 50 mm from the edge of all corners.

Fasteners must penetrate not less than 30 mm into the timber frame

Wall cladding may be fixed through timber or metal battens attached to the wall frame in accordance with AS 1684.2, AS 1684.3, AS 1684.4 or NASH standard as appropriate (see fixing requirements for roof battens) so long as the minimum penetration into the wall frame is achieved.

Tables

Same wording in ABCB Housing Provisions 2022. See ABCB Housing Provisions 2022 7.5.4.