(1) The entry of water, foul gases, sewerage and sullage from a sanitary plumbing system into buildings must be avoided.

(2) The entry of foul gases from a sanitary plumbing system into buildings must be avoided, such that—

at pressures of up to ±375 Pa, water trap seals will not be reduced to depths less than

70 mm for trap seals in pressurised rooms; and

25 mm for all other applications; or

an equivalent level of safety to human health is achieved as a system complying with (a).

(3) The entry of surface water, sub-surface water and stormwater into a sanitary plumbing system must be avoided.

Changed since NCC 2022. See NCC 2022 Volume Three C1P6, or show what changed.

A sanitary plumbing system must avoid — (1) The entry of water, foul gases, sewerage and sullage from the a sanitary plumbing system into buildings; and buildings must be avoided. (2) The entry of foul gases from the a sanitary plumbing system into buildings, buildings must be avoided, such that — at pressures of up to ±375 Pa, … depths less than 70 mm for trap seals in pressurised rooms rooms; and 25 mm for all other applications; or an equivalent level of safety to human health is achieved as a system complying to (i); and with (a). (3) The entry of surface water, subsurface sub-surface water and stormwater into the system. a sanitary plumbing system must be avoided.

Removed words are struck through; added words are highlighted. Comparison of the text only.