Deemed-to-Satisfy Provision · NCC 2025 Volume One

C2D9 Lightweight construction

Part C2 Fire resistance and stability · NCC 2019: C1.8

Open C2D9 on NCC Online ↗

(1) Lightweight construction must comply with Specification 6 if it is used in a wall system—

that is required to have an FRL; or

for a lift shaft, stair shaft or service shaft or an external wall bounding a public corridor including a non fire-isolated passageway or non fire-isolated ramp, in a spectator stand, sports stadium, cinema or theatre, railway station, bus station or airport terminal.

(2) If lightweight construction is used for the fire-resisting covering of a steel column or the like, and if—

the covering is not in continuous contact with the column, then the void must be filled solid, to a height of not less than 1.2 m above the floor to prevent indenting; and

the column is liable to be damaged from the movement of vehicles, materials or equipment, then the covering must be protected by steel or other suitable material.

New in NCC 2025. No C2D9 in NCC 2022 Volume One; it may have moved or been renumbered.
Can't meet C2D9? A Performance Solution must meet the Performance Requirements it satisfies: C1P1, C1P2, C1P3, C1P4, C1P5, C1P6, C1P7, C1P8, C1P9. Start a Performance Solution →

Defined terms used