New South Wales variation · NCC 2025 Volume One

NSW J1V3 Verification using a reference building

NSW Part J1 Energy efficiency performance requirements · varies J1V3 Verification using a reference building

Open on NCC Online ↗

Insert NSW clause J1V3 in clause J1V3 as follows:

(1) For a Class 3, 5, 6, 7, 8 or 9 building, compliance with NSW J1P1 is verified when—

it is determined that—

the annual greenhouse gas emissions of the proposed building are not more than 97% of the annual greenhouse gas emissions of a reference building when the proposed building is modelled with the proposed services; and

the annual greenhouse gas emissions of the services of the proposed building are not more than the annual greenhouse gas emissions of a the services of the reference building when the proposed building is modelled with the same services as the reference building; and

in the proposed building—

if a Class 5 building, a thermal comfort level of between a Predicted Mean Vote of -1 to +1 is achieved across not less than 95% of the floor area of all occupied zones for not less than 98% of the annual hours of operation of the building; or

a dry bulb room temperature is maintained across not less than 95% of the floor area of all occupied zones other than any room containing an indoor swimming pool, for not less than 95% of the annual hours of operation between—

18°C and 25°C for conditioned spaces with transitory occupancy; and

21°C and 24°C for all other conditioned spaces; or

in climate zone 1, the 98th percentile zone cooling load across the hours of operation does not exceed 110% of the 98th percentile load in the corresponding zone of the reference building, across 95% of the assessable floor area; or

in climate zone 8, the 98th percentile zone heating load across the hours of operation does not exceed 110% of the 98th percentile load in the corresponding zone of the reference building, across 95% of the assessable floor area; or

in climate zones 2 to 7—

the 98th percentile zone cooling load across the annual hours of operation does not exceed 120% of the 98th percentile load of the corresponding zone of the reference building, across 95% of the assessable floor area; and

the 98th percentile zone heating load across the annual hours of operation does not exceed 120% of the 98th percentile load of the corresponding zone of the reference building, across 95% of the assessable floor area; and

the building complies with the additional requirements in Specification 33.

(2) The calculation method used for (1) must comply with—

ANSI/ASHRAE Standard 140; and

Specification 34; and

Specification 48.

Changed since NCC 2022. See NCC 2022 Volume One NSW J1V3, or show what changed.

Insert NSW clause J1V3 in clause J1V3 as follows: (1) For a Class 3, 5, 6, 7, 8 or 9 building, compliance with NSW J1P1 is verified when — it is determined that — the annual greenhouse gas emissions of the proposed building are not more than 97% of the annual greenhouse gas emissions of a reference building when the proposed building is modelled with the proposed services; and the annual greenhouse gas emissions of the services of the proposed building are not more than the annual greenhouse gas emissions of a the services of the reference building when — the proposed building is modelled with the proposed services; and the proposed building is modelled with the same services as the reference building; and in the proposed building — if a Class 5 building, a thermal comfort level of between a Predicted Mean … 98% of the annual hours of operation of the building; or a dry bulb room temperature is maintained across not less than 95% of the floor area of all occupied zones other than any room containing an indoor swimming pool, for not less than 95% of the annual hours of operation between — 18°C and 25°C for conditioned spaces with transitory occupancy; and 21°C and 24°C for all other conditioned spaces; or in climate zone 1, the 98th percentile zone cooling load across the hours of operation does not exceed 110% of the 98th percentile load in the corresponding zone of the reference building, across 95% of the assessable floor area; or in climate zone 8, the 98th percentile zone heating load across the hours of operation does not exceed 110% of the 98th percentile load in the corresponding zone of the reference building, across 95% of the assessable floor area; or in climate zones 2 to 7 — the 98th percentile zone cooling load across the annual hours of operation does not exceed 120% of the 98th percentile load of the corresponding zone of the reference building, across 95% of the assessable floor area; and the 98th percentile zone heating load across the annual hours of operation does not exceed 120% of the 98th percentile load of the corresponding zone of the reference building, across 95% of the assessable floor area; and the building complies with the additional requirements in Specification 33. (2) The annual greenhouse gas emissions of the proposed building may be offset by — renewable energy generated and used on site; and another process such as reclaimed energy, used on site. (3) The calculation method used for (1) and (2) must comply with — ANSI/ASHRAE Standard 140; and Specification 34. 34; and Specification 48.

Removed words are struck through; added words are highlighted. Comparison of the text only.