Specification clause · NCC 2025 Volume One
S5C8 Enclosure of shafts
Specification 5 Fire-resisting construction · NCC 2019: Spec C1.1: 2.7
(1) Shafts required to have an FRL must be enclosed at the top and bottom by construction having an FRL not less than that required for the walls of a non-load bearing shaft in the same building.
(2) The provisions of (1) need not apply to—
the top of a shaft extending beyond the roof covering, other than one enclosing a fire-isolated stairway or ramp; or
the bottom of a shaft if it is non-combustible and laid directly on the ground.
Same wording in NCC 2022 Volume One. See NCC 2022 Volume One S5C8.