Housing Provisions clause · ABCB Housing Provisions 2022

10.2.28 Installation of internal membranes

Part 10.2 Wet area waterproofing

Open 10.2.28 on NCC Online ↗

(1) Where a shower has a hob the membrane must be brought over the top of the hob, down the outside face and terminate not less than 50 mm onto the floor (see Figure 10.2.16).

(2) Where the shower has a waterstop, the membrane must be brought to the top of the finished floor, except where it is under a framed shower screen where it must terminate not less than 5 mm above the finished tile surface (see Figure 10.2.17 and Figure 10.2.18).

Same wording in ABCB Housing Provisions 2025. See ABCB Housing Provisions 2025 10.2.28.