ABCB Housing Provisions 2022
Part 10.2 Wet area waterproofing
32 clauses · Open on NCC Online ↗
- 10.2.1 Wet areas SABuilding elements in wet areas within a building must be protected with a waterproofing system. (2) The waterproofing system in (1) must be either…
- 10.2.2 Shower area (enclosed and unenclosed)For a shower area with a hob, step-down or level threshold, the following applies: The floor of the shower area must be waterproof, including any…
- 10.2.3 Area outside shower areaFor concrete, compressed fibre-cement and fibre-cement sheet flooring, the floor of the room must be water resistant. (2) For timber floors…
- 10.2.4 Areas adjacent to baths and spas without showersFor areas adjacent to all baths and spas, the following applies: For concrete, compressed fibre-cement and fibre-cement sheet flooring, the floor of…
- 10.2.5 Other areasFor walls adjoining other types of vessels (e.g. sink, basin or laundry tub), the following applies: Walls must be water resistant to a height of…
- 10.2.6 Waterproofing systemsFor the purposes of this Part, a waterproofing system is deemed— waterproof, if it complies with (2); or water resistant, if it complies with (3).…
- 10.2.7 MaterialsWhere required to be installed in accordance with 10.2.2 to 10.2.6, materials used in wet areas forming a waterproofing system must be either…
- 10.2.8 Materials — waterproofThe following materials used in waterproofing systems are deemed to be waterproof: Stainless steel. Flexible waterproof sheet flooring material with…
- 10.2.9 Materials — water resistant substratesThe following materials are deemed to be water resistant: For walls: Concrete complying with AS 3600, treated to resist moisture movement. Cement…
- 10.2.10 Materials — water resistant surface materialsThe following surface materials are deemed to be water resistant: For walls: Thermosetting laminate. Pre-decorated compressed fibre-cement sheeting…
- 10.2.11 Construction of wet areas — wall and floor substrate materialsFor the purposes of this Part, materials used in wall and floor substrates must comply with 10.2.9.
- 10.2.12 Construction of wet area floors — fallsWhere a floor waste is installed— the minimum continuous fall of a floor plane to the waste must be 1:80; and the maximum continuous fall of a floor…
- 10.2.13 Construction of wet areas — wall and floor surface materialsFor the purposes of this Part, wall and floor surface materials must comply with 10.2.10.
- 10.2.14 Shower area requirementsShower areas must be designed as either enclosed or unenclosed— to include a floor waste with falls complying with 10.2.12; and with a— stepdown…
- 10.2.15 Stepdown showersFor stepdown showers, the highest finished floor level of the shower area must be stepped down a minimum of 25 mm lower than the finished floor…
- 10.2.16 Hob constructionHobs must be constructed of— masonry; or concrete; or autoclaved aerated concrete; or extruded polyurethane foam, in accordance with Figure 10.2.16.…
- 10.2.17 Enclosed showers with level threshold (without hob or set down)For enclosed showers without a stepdown or a hob, at the extremity of the shower area, a waterstop must be positioned so that its vertical leg…
- 10.2.18 Unenclosed showersUnenclosed showers must be constructed as follows: A waterstop must be installed a minimum horizontal distance of 1500 mm from the shower rose. The…
- 10.2.19 Preformed shower basesPreformed shower bases must— have an upturn lip (see Figure 10.2.19a and Figure 10.2.19b); and be recessed into the wall to allow the water…
- 10.2.20 Baths and spasBaths and spas, except freestanding baths and spas, must— have an upturn lip; and be recessed into the wall (see Figure 10.2.20); and have the water…
- 10.2.21 Membrane installation for screedWhere a screed is used in conjunction with a waterproof membrane, the waterproof membrane can be installed either above or below the tile bed or…
- 10.2.22 Substrate surface preparation for application of membraneThe substrate surface area where a membrane is to be applied must— be clean and dust free; and free of indentations and imperfections.
- 10.2.23 PenetrationsPenetrations within shower areas must comply with the following: Penetrations for taps, shower nozzles and the like must be waterproofed by sealing…
- 10.2.24 Flashings/junctionsFlashings must be installed in accordance with 10.2.2 to 10.2.5 and the following: Perimeter flashing to wall/floor junctions must have a— vertical…
- 10.2.25 Shower area floor membrane applicationFor hobless showers, or showers with hobs or stepdowns, the membrane must be applied over the floor and up the vertical face of the wall substrate…
- 10.2.26 Shower area membrane requirements for wall sheeting substratesWhere wall sheeting is used with an external membrane system in a shower area it must be waterproof to prevent water movement by capillary action.…
- 10.2.27 Bond breaker installation for bonded membranesBond breakers must be installed at all wall/wall, wall/floor, hob/wall junctions and at movement joints where the membrane is bonded to the…
- 10.2.28 Installation of internal membranesWhere a shower has a hob the membrane must be brought over the top of the hob, down the outside face and terminate not less than 50 mm onto the…
- 10.2.29 Membrane to drainage connectionMembrane drainage connections in concrete floors must comply with one of the following: A drainage flange must be installed with the waterproofing…
- 10.2.30 Drainage riser connectionWhere a preformed shower base is used, the drainage riser must be connected to the tray with a waterproof joint. (2) Where an in situ shower tray is…
- 10.2.31 Door jambs on tiled floorsWhere the bottom of a door jamb does not finish above the floor tiling, the portion of the door frame below the floor tiling must be waterproofed to…
- 10.2.32 Shower screensFor a shower with a hob, the shower screen must be installed flush with the shower area side of the hob or overhang into the shower area. (2) For a…