4.2.4 Filling under concrete slabs
Part 4.2 Footings, slabs and associated elements · NCC 2019: 3.2.2.2
Filling placed under a slab (except where the slab is suspended) must comply with the following:
Filling must be either controlled fill or rolled fill as follows:
Sand used in controlled fill or rolled fill must not contain any gravel size material and achieve a blow count of 7 or more per 300 mm using the test method described in AS 1289.6.3.3.
Clay used in controlled fill or rolled fill must be moist during compaction.
Controlled fill:
Sand fill up to 800 mm deep — well compacted in layers not more than 300 mm deep by vibrating plate or vibrating roller.
Clay fill up to 400 mm deep — well compacted in layers of not more than 150 mm by a mechanical roller.
Rolled fill:
Sand fill up to 600 mm deep — compacted in layers of not more than 300 mm by repeated rolling by an excavator or other suitable mechanical equipment.
Clay fill up to 300 mm deep — compacted in layers of not more than 150 mm by repeated rolling by an excavator or similar machine.
A level layer of clean quarry sand must be placed on top of the fill, with a depth of not less than 20 mm.
A graded stone termite management system complying with Part 3.4 may be substituted for the sand required in (b).