New South Wales variation · NCC 2025 Volume Three

NSW B1D3 General requirements

NSW Part B1 Cold water services · varies B1D3 General requirements

Open on NCC Online ↗

Delete clause B1D3 and insert NSW B1D3 as follows:

(1) A cold water service must be in accordance with AS/NZS 3500.1, with the following variations

Clause 5.4.2: insert subclause (m) Where valves are located below ground within the property boundary, they shall be provided with a surface box and riser. The box lid shall be permanently marked with a “W”.

(2) Notwithstanding (1), plastic pipes and fittings must not be used in a cold water service above-ground to supply combined sprinkler and hydrant systems.

Changed since NCC 2022. See NCC 2022 Volume Three NSW B1D3, or show what changed.

Delete clause B1D3 and insert NSW B1D3 as follows: (1) A cold water service must be in accordance with AS/NZS 3500.1, with the following additions to clause variations Clause 5.4.2: (l) insert subclause (m) Where valves are located below ground within the property boundary, … The box lid shall be permanently marked with a “W”. (2) Notwithstanding (1), plastic pipes and fittings must not be used in a cold water service above-ground to supply combined sprinkler and hydrant systems.

Removed words are struck through; added words are highlighted. Comparison of the text only.