Deemed-to-Satisfy Provision · NCC 2025 Volume One
D3D16 Thresholds
Part D3 Construction of exits · NCC 2019: D2.15, NSW D2.15(d), (e), SA D2.15(e)
Varied in NSW. Check the variation for your state.
The threshold of a doorway must not incorporate a step or ramp at any point closer to the doorway than the width of the door leaf unless the doorway opens to an external space; and—
where the doorway serves an area required to be accessible by Part D4, it is provided with a threshold ramp or step ramp in accordance with AS 1428.1; or
where (a) does not apply, the door sill is not located below, and is not more than 190 mm above, the finished surface of the ground, balcony, or the like to which the doorway opens.
Exemptions
D3D16 does not apply to a plant room, machinery room, or the like.
New in NCC 2025. No D3D16 in NCC 2022 Volume One; it may have moved or been renumbered.
Can't meet D3D16? A Performance Solution must meet the Performance Requirements it satisfies: D1P1, D1P2, D1P3, D1P4, D1P5, D1P6, D1P8, D1P10, D1P9. Start a Performance Solution →