E2D2 Application of part

Part E2 Smoke hazard management · NCC 2019: E2.1

Open E2D2 on NCC Online ↗

(1) The Deemed-to-Satisfy Provisions of this Part do not apply to—

an open-deck carpark; or

an open spectator stand; or

a Class 8 electricity network substation with a floor area not more than 200 m2, located within a multi-classified building.

(2) In addition to the Deemed-to-Satisfy Provisions of E2D3 to E2D13, the following specific Deemed-to-Satisfy Provisions apply to the following Class 6 and Class 9b buildings:

For Class 6 buildings, in fire compartments more than 2000 m2—

not containing an enclosed common walkway or mall serving more than one Class 6 sole-occupancy unit — must comply with E2D14; or

containing an enclosed common walkway or mall serving more than one Class 6 sole-occupancy unit — must comply with E2D15.

For Class 9b assembly buildings—

nightclubs, discotheques and the like — must comply with E2D16; and

exhibition halls — must comply with E2D17; and

theatres and public halls — must comply with E2D18; and

theatres and public halls (not covered by E2D18) including lecture theatres and cinema/auditorium complexes — must comply with E2D19; and

other assembly buildings (not listed in (i) to (iv)) excluding schools — must comply with E2D20.

(3) The smoke exhaust and smoke-and-heat vent provisions of this Part do not apply to any area not used by occupants for an extended period of time such as a storeroom with a floor area less than 30 m2, sanitary compartment, plant room or the like.

Same wording in NCC 2025 Volume One. See NCC 2025 Volume One E2D2.