Deemed-to-Satisfy Provision · NCC 2025 Volume Two

H2D1 Deemed-to-Satisfy Provisions

Part H2 Damp and weatherproofing

Open H2D1 on NCC Online ↗

(1) Where a Deemed-to-Satisfy Solution is proposed, Performance Requirements H2P1 to H2P4 are satisfied by complying with H2D2 to H2D8.

(2) Where a Performance Solution is proposed, the relevant Performance Requirements must be determined in accordance with A2G2(3) and A2G4(3) as applicable.

Changed since NCC 2022. See NCC 2022 Volume Two H2D1, or show what changed.

(1) Where a Deemed-to-Satisfy Solution is proposed, Performance Requirements H2P1 to H2P3 H2P4 are satisfied by complying with H2D2 to H2D8. (2) Performance RequirementH2P4 must be complied with. (3) Where a Performance Solution is proposed, the relevant Performance Requirements must be determined in accordance with A2G2(3) and A2G4(3) as applicable. Notes There are no Deemed-to-Satisfy Provisions for H2P4.

Removed words are struck through; added words are highlighted. Comparison of the text only.

Clauses referred to

Defined terms used