(1) Exterior artificial lighting attached to or directed at the facade of a building, must—
be controlled by—
a daylight sensor; or
a time switch that is capable of switching on and off electric power to the system at variable pre-programmed times and on variable pre-programmed days; and
when the total lighting load exceeds 100 W—
use LED luminaires for 90% of the total lighting load; or
be controlled by a demand-operated control in accordance with Specification 40; or
when used for decorative purposes, such as façade lighting or signage lighting, have a separate time switch in accordance with Specification 40.
(2) The requirements of (1)(b) do not apply to the following:
Emergency lighting in accordance with Part E4.
Lighting around a detention centre.
Changed since NCC 2022 (minor wording). See NCC 2022 Volume One J7D6, or show what changed.