NCC 2025 Volume Three
Part C2 Sanitary drainage systems
21 clauses · Open on NCC Online ↗
- C2O1 ObjectiveThe Objective of this Part is to— safeguard people from illness, injury or loss (including loss of amenity) due to the failure of a sanitary…
- C2F1 Disposal systemSanitary fixtures and sanitary appliances must be provided with an adequate disposal system that does not impact adversely on occupants of the…
- C2F2 Swimming pool wastewater disposalAdequate means for the disposal of swimming pool water and drainage is to be provided for each swimming pool.
- C2P1 DisposalSewage must be conveyed through a sanitary drainage system to an approved disposal system authorised by an authority having jurisdiction.
- C2P2 Swimming pool drainage NTAn adequate means of draining a swimming pool must be designed and installed in a way that will not cause illness to people. (2) An adequate means…
- C2P3 AccessAccess must be provided to components of a sanitary drainage system that require maintenance or replacement including mechanical devices, controls…
- C2P4 VentilationA sanitary drainage system must ensure there is adequate ventilation to avoid foul air and gases accumulating in the sanitary drainage and sewerage…
- C2P5 ContaminationThe entry of water, foul gases, sewerage and sullage from a sanitary drainage system into buildings must be avoided. (2) A sanitary drainage system…
- C2P6 Uncontrolled dischargeAny failure or uncontrolled discharge from a sanitary drainage system must be avoided.
- C2P7 Damage NSWDamage to sanitary drainage systems from superimposed loads must be avoided. (2) Damage to sanitary drainage systems from ground movement must be…
- C2V1 Velocity and liquid-to-air ratioCompliance with C2P1 is achieved if the sanitary drainage system is designed to operate with— a liquid-to-air ratio of between 1 to 1 and 0.65 to…
- C2V2 Pressure testingCompliance with C2P1 is achieved if the sanitary drainage system passes one or more of the pressure tests set out in AS/NZS 3500.2.
- Table C2V3a Frequency factorsNCC building class | NCC building class example | Frequency factor (K) | Time interval between fixture use averaged over peak period (s) Class 1 |…
- Table C2V3b Discharge unitsFixture | Discharge Units (DU) Basin | 0.3 Bath (with shower) | 0.5 Bath (without shower) | 0.6 Bidet | 0.3 Shower (single) | 0.4 Urinal (wall-hung)…
- C2V3 Determination of sanitary drainage wastewater flowratesCompliance with C2P1 for pipe sizing is verified for each sanitary drainage pipework section when the design flow rate is not less than— the…
- C2V4 Sanitary drainage designCompliance with C2P1 for main drains and branch drains is verified if (2) to (4) are complied with. (2) Sanitary drainage pipework shall be sized in…
- C2D1 Deemed-to-Satisfy ProvisionsWhere a Deemed-to-Satisfy Solution is proposed, Performance Requirements C2P1 to C2P7 are satisfied by complying with C2D2 to C2D5. (2) Where a…
- C2D2 Invert levelsThe invert level of a trap or gully weir must be a minimum of 10 mm higher than the soffit of the pipe to which it connects.
- C2D3 Swimming pool drainage NTWhere pumped discharge from a swimming pool discharges into a sanitary drainage system it must be in accordance with AS/NZS 3500.2.
- C2D4 General requirements NSW SA TAS VIC WAA sanitary drainage system must be in accordance with AS/NZS 3500.2.
- C2D5 Bushfire prone areasA sanitary drainage system in a designated bushfire prone area must be in accordance with AS 3959.