Deemed-to-Satisfy Provision · NCC 2025 Volume One

J7D2 Application of Part

Part J7 Artificial lighting and power · NCC 2019: J6.1, NSW J(A)4.1

Open J7D2 on NCC Online ↗

J7D3, J7D4 and J7D6(1)(b) do not apply to a Class 8 electricity network substation.

Same wording in NCC 2022 Volume One. See NCC 2022 Volume One J7D2.
Can't meet J7D2? A Performance Solution must meet the Performance Requirements it satisfies: J1P1, J1P2, J1P3, J1P4. Start a Performance Solution →

Clauses referred to

Defined terms used