Deemed-to-Satisfy Provision · NCC 2022 Volume Three

C2D3 Swimming pool drainage

Part C2 Sanitary drainage systems · NCC 2019: C2.3

Open C2D3 on NCC Online ↗

Pumped discharge from a swimming pool must connect to the sanitary drainage system in accordance with AS/NZS 3500.2.

Changed in NCC 2025. See NCC 2025 Volume Three C2D3, or show what changed.

Pumped Where pumped discharge from a swimming pool must connect to the discharges into a sanitary drainage system it must be in accordance with AS/NZS 3500.2.

Removed words are struck through; added words are highlighted. Comparison of the text only.

Can't meet C2D3? A Performance Solution must meet the Performance Requirements it satisfies: C2P1, C2P2, C2P3, C2P4, C2P5, C2P6, C2P7. Start a Performance Solution →

Defined terms used