- J4D1 Deemed-to-Satisfy Provisions NSWWhere a Deemed-to-Satisfy Solution is proposed, Performance Requirements J1P1 to J1P4 are satisfied by complying with— J2D2; and J3D2 to J3D15; and…
- J4D2 Application of Part NSWThe Deemed-to-Satisfy Provisions of this Part apply to building elements forming the envelope of a Class 3 to 9 building other than J4D3(5), J4D4,…
- J4D3 Thermal construction — generalWhere required, insulation must comply with AS/NZS 4859.1 and be installed so that it— forms a continuous barrier with ceilings, walls, bulkheads,…
- J4D4 Roof and ceiling constructionA roof or ceiling must achieve a Total R-Value greater than or equal to— for a Class 5, 6, 7, 8 or 9b building or a Class 9a building other than a…
- Table J4D5 Roof lights – Total system SHGCRoof light shaft index Note 1 | Total area of roof lights up to 3.5% of the floor area of the room or space | Total area of roof lights more than…
- J4D5 Roof lightsRoof lights must have— a total area of not more than 5% of the floor area of the room or space served; and transparent and translucent elements,…
- Table J4D6a Maximum Total System U-Value of wall-glazing constructionClimate zone | Class 5, 6, 7, 8, 9b building or a Class 9a building other than a ward area | Class 3 or 9c building or a Class 9a ward area 1 | 1.6…
- Table J4D6b Minimum wall Total R-Value - Wall area 80% or more of wall-glazing construction areaClimate zone | Class 5, 6, 7, 8 or 9b building or a Class 9a building other than a ward area | Class 3 or 9c building or Class 9a ward area 1 | 3.0…
- Table J4D6c Maximum wall-glazing construction solar admittance - Class 5, 6, 7, 8 or 9b building or Class 9a building other than a ward areaClimate zone | Eastern aspect solar admittance | Northern aspect solar admittance | Southern aspect solar admittance | Western aspect solar…
- Table J4D6d Maximum wall glazing construction solar admittance - Class 3 or 9c building or Class 9a ward areaClimate zone | Eastern aspect solar admittance | Northern aspect solar admittance | Southern aspect solar admittance | Western aspect solar…
- J4D6 Walls and glazingThe Total System U-Value of wall-glazing construction, including wall-glazing construction which wholly or partly forms the envelope internally,…
- Table J4D7 Floors – Minimum Total R-ValueLocation | Climate zone 1— upwards heat flow | Climate zones 2 and 3 — upwards and downwards heat flow | Climate zones 4, 5, 6 and 7 — downwards…
- J4D7 FloorsA floor must achieve the Total R-Value specified in Table J4D7. (2) For the purposes of (1), a slab-on-ground that does not have an in-slab heating…