NSW J8D1 Deemed-to-Satisfy Provisions
NSW Part J8 Heated water supply and swimming pool and spa pool plant · varies J8D1 Deemed-to-Satisfy Provisions
Delete subclause J8D1(1) and insert NSW J8D1(1) as follows:
(1) Where a Deemed-to-Satisfy Solution is proposed, Performance Requirements NSW J1P1 and NSW J1P4 are satisfied by complying with—
NSW J2D2; and
Changed since NCC 2022. See NCC 2022 Volume One NSW J8D1, or show what changed.
Delete subclause J8D1(1) and insert NSW J8D1(1) as follows: (1) Where a Deemed-to-Satisfy Solution is proposed, Performance Requirements NSW J1P1 to and NSW J1P7 J1P4 are satisfied by complying with — NSW J2D2; and NSW J3D2 to J3D10; and NSW J4D2 to J4D7; and NSW J5D2 to J5D8; and NSW J6D2 to J6D13; and NSW J7D2 to J7D9; and NSW J8D2 to J8D5; and NSW J8D4; and J9D2 to J9D5.
Removed words are struck through; added words are highlighted. Comparison of the text only.